|
How to
perform a schedule update
Prior to being
able to successfully provide schedule updates, your organization
should become familiar with the process. Your
field personnel should have a list of
their activity numbers and know
what they mean. They will need to understand the importance of
documenting the starting and finishing of an activity. Click
here for some scheduling basics.
For the purpose of
CPM scheduling you and your field personnel should understand the
following;
An activity ACTUALLY becomes complete or 100% when
it ceases to PREVENT the start of the successor or following dependant
activity. FOR EXAMPLE: A drywall partition
is all done except for a small area for a drinking fountain. The
painting of the wall has started and completed all except the area at
the drinking fountain. For the purpose of the schedule this activity
is 100% because it is no longer preventing the successor from
starting. However,
you should not take the liberty of 100% an activity that is incomplete
without remarking to the scheduler that a work-around is in progress.
STEP
1:
Gather the necessary information
and resources. Including Original schedule or
last updated schedule, field reports, material delivery information,
submittal approval information, etc.
STEP 2:
Obtain/Use the data date
from the Contractor or Lead Contractor.
This is the date that is the SNAPSHOT of the project progress.
All
information is to be relative to that date.
STEP 3:
Using a ruler draw a vertical line on the schedule that coincides with
the data date using the time-scale that is at the top of the
schedule. Click here for an
illustration.
STEP 4:
The activities that are on the LEFT
of the line should have been completed by the
data date.
Using the activities on the LEFT as a LIST of MUST UPDATE, gather and
report the information on these first. Then proceed to determine if
other activities need to be updated. Click
here for a flowchart.
For activities that have
started and finished
before the data date, you need three
(3) items. The activity number and
two dates. Record the activity number and
the two dates
on the update form. You do not have to insert 100% in the percentage
since you have start and finish dates. The software will know it’s
100%. It is important for liability sake that you have
accurate dates.
The state of Ohio contracting rules
require a weekly update to be provided to the lead contractor. If your
field people go much beyond a week the information is likely to be
suspect. The web based update uses each Monday of a week for a data
date. Very important actual
start and finish dates can only be equal to or earlier than the data
date. Do not try to
figure out and project when an activity will be completed. That is the
computers job. The format for dates is YYYYMMDD, or 20070101 for
January 1, 2007.
For activities
that have
started but are not finished, you
need four (4) items.
These are activity no., start date, remaining duration and percentage
complete. The remaining duration is the
days after the data date.
The percentage has nothing to do with time only units. When reporting
remaining duration do not report a longer duration that the original
duration assigned to the activity. If you find that there is a
problem, contact the scheduler and report the problem.
For activities that have neither started nor finished,
record nothing.
For activities that you wish to revise the
duration, record the activity no., and remaining duration. Provide
an explanation to justify the change.
If you want a logic change you will need to provide a
drawing that shows the original and revised logic. You will need to
provide all information on affected activities. This would entail
changes to the successors and predecessors for activities.
Change order work is likely to require such schedule changes.
STEP 5:
After completing the SCHEDULE UPDATE FORM,
either fax or email it to the lead contractor.
STEP 6:
It may be that when your information is entered that a new critical
path will be identified. The schedule still may show you as late and
will require more information from you. An interim schedule will be
provided by the LEAD CONTRACTOR to identify the areas of concern. Need
more information: Contact the LEAD CONTRACTOR. If there is
inconsistence in your reporting it will come back to haunt you. You
should keep records of what you have already submitted and your
current update should not indicate negative progress.
Update form
definitions:
Data Date:
This is the date selected for the time
'snap-shot' of the project.
Activity Number:
This is a unique number that identifies a construction activity.
% Complete:
This is the percentage of completion of
the units that are assigned to the resources. It does not apply to
time, unless it is a time related activity such as SUBMIT, APPROVE FAB
& DELIVER.
Remaining Duration:
This is the number of work days needed
to complete an activity after the data date.
Actual Start Date:
This is exactly what is says.
Actual Finish Date:
This is exactly what is says.
|