Sub / Vendor Name:
Your Name:
Project/Location:
Your E-Mail Address:
Phone:
Fax:
Date of Inquiry:
Today
Work Completed thru date:
To determine billing period
Your Invoice Number:
Date of Invoice:
Are all Certified Payrolls submitted including up to the last payroll period:
Check YES or NO
YES NO
Failure to submit payrolls can cause government to withhold entire contract billings! (NOT A VENDOR Question)
Have you returned all notarized interim lien waiver(s) for all previous payments:
This was mailed along with the check!
Have you returned the notarized final waiver for the FINAL payment:
Only on a FINAL payment request
If previously requested, have you furnished the names & phone nos., for us to verify that materials have been paid for:
Enables us to make sure that there will be no claims against us for unpaid subs and vendors. Not generally required for bonded subcontractors, or VENDORS.
Have your subcontractors and vendors been paid from previous payments and their waivers been provided to us:
Enables us to make sure that there will be no claims against us for unpaid subs and vendors. (NOT A VENDOR QUESTION)
Have you signed and returned all change orders for which you are requesting payment:
You cannot invoice for a change order that has not been modified to your subcontract.
Have you submitted and received approval on a schedule of values upon which your billing is based:
Must be submitted and approved prior to any payments! Not required if contact is less that $3,000
Was your invoice submitted in triplicate before the contractual due date:
This enables us to bill the owner the proper amount in our billing.
Have you read and understand the payment terms of the subcontract/PO and not assumed that it is your 'standard terms' :
Terms are generally 'Pay when paid'. See Purchase Orders for terms for vendors.